How much delay deprives buyer of substantially the whole benefit of the contract? (Court of Appeal)

In Urban I (Blonk Street) Ltd v Ayres and another [2013] EWCA Civ 816, the Court of Appeal held that a developer's delay of approximately one month did not deprive a buyer of substantially the whole benefit of the contract for a lease of a flat that was being built, and so the buyer was not entitled to terminate the agreement.

Get full access to this document with a free trial

Try free and see for yourself how Practical Law resources can improve productivity, efficiency and response times.

About Practical Law

This document is from Thomson Reuters Practical Law, the legal know-how that goes beyond primary law and traditional legal research to give lawyers a better starting point. We provide standard documents, checklists, legal updates, how-to guides, and more.

Learn more
  • Expert Guidance

    650+ full-time experienced lawyer editors globally create and maintain timely, reliable and accurate resources across all major practice areas.

  • Trust

    83% of customers are highly satisfied with Practical Law and would recommend to a colleague.

  • Improve Response Time

    81% of customers agree that Practical Law saves them time.

End of Document
Resource ID 1-533-8345
© 2024 Thomson Reuters. All rights reserved.
Published on 11-Jul-2013
Resource Type Legal update: archive
Jurisdictions
  • England
  • Wales
Related Content