Questions and answers for the Berwin Leighton Paisner construction law Christmas quiz 2010.
Questions and answers
This article sets out the questions and answers for the Berwin Leighton Paisner construction Christmas quiz 2010.
The answers are revealed by clicking on the note below each question.
1. Claims in tort
A contractor enters into a contract with Own Co (the owner) to build and sell a new building to Own Co. The building contains a latent defect that renders it dangerous to persons or other property. Any action under the contract is time barred. Assume that an action in tort is not time barred. Which of the following statements is true?
(a) The contractor owes a duty of care in tort in relation to defects that cause either personal injury or physical damage to property other than the property itself.
(b) The contractor does not owe a duty of care in tort not to cause economic loss to Own Co.
(c) The contractor does owe a duty of care in tort not to cause economic loss to Own Co.
(d) A contractor cannot owe concurrent duties of care in contract and tort.
(e) In the recent case of Linklaters Business Services v McAlpine Ltd and others [2010] EWHC 2931 (TCC), Akenhead J confirmed that there is no place for the complex structure theory in cases such as the one outlined above.
Statement (a) is correct, as it reflects the principles of Donoghue v Stevenson [1932] AC 562.
Statements (b) and (c) cover a grey area, but (c) is currently correct on the basis of authorities. In Mr J A Robinson v PE Jones (Contractors) Ltd [2010] EWHC 102 at paragraphs 10-13, the Technology and Construction Court (TCC) addressed the question of whether a contractor can owe its client a concurrent duty of care in tort in relation to economic loss (see Legal update, Home owner's claim statute barred as no duty of care owed by the builder).
Statement (d) is incorrect. It is well established that contractors can owe concurrent duties of care in contract and tort (see paragraphs 36-52 of the judgment in Robinson v PE Jones for a review of these authorities).
In relation to statement (e), Akenhead J found that the complex structure theory did not apply in the Linklaters case because in the case of insulated chilled water pipe work, the piping and the insulation were two components which went to make up one installation, so that damage to the pipework (caused by the defective insulation) is damage to the "thing itself" and not damage to "other property". The complex structure theory therefore cannot apply. (For more information on the Linklaters case, see Legal update, Claim against sub-sub-contractor in Linklaters' litigation fails (full update).)
(a) The FIDIC Silver Book imposes a fitness for purpose obligation on the contractor whereas the FIDIC Red Book does not.
(b) Under the FIDIC Silver Book the contractor is entitled to an extension of time where the works are or will be delayed by any of the following:
(i) variation;
(ii) any other provision; or
(iii) any delay, impediment or prevention caused by the employer.
(c) Under the FIDIC Red Book the contractor takes responsibility for both verifying and interpreting the site data made available by the employer.
(d) Under the FIDIC Silver Book, the engineer plays a crucial role by acting as the employer's agent. For example, for ordering variations, making decisions as regards payment certificates and resolving disputes between the employer and contractor.
Statement (a) is acceptable (in the Christmas spirit) but, strictly speaking, the answer is none.
The FIDIC form comes closest to this object, but does not fulfil the objective of being a true "turnkey" contract as suggested by its full title. Under clause 5.1 the employer retains responsibility for:
Elements of the employer's requirements expressed to be immutable or the responsibility of the employer.
Definitions of intended purposes of the works.
Criteria for the testing and performance of the completed works.
Portions, data or information which cannot be verified by the contractor (except as otherwise stated in the contract).
The IChemE contract makes provision for contractor design, but each party remains responsible for its own design element. The balance of responsibility under a particular contract needs to be ascertained by review of the specifications. The picture can become cloudy where both parties have worked on a particular design element. For more information on the IChemE suite of contracts, see Practice note, IChemE contracts.
Under the IMechE contract, the contractor is responsible for the detailed design of the plant in accordance with the specification but, to the extent that detailed designs are provided by the employer (or the "engineer" on behalf of the employer), the contractor will not be responsible for such design if, "within a reasonable time after receipt", he gives notice to the engineer disclaiming responsibility. The drafting is not entirely clear, but is based on the presumption that the specification is prepared by the engineer on behalf of the employer. The detailed design undertaken by the contractor post tender and detailed design by or on behalf of the employer will only occur where there is a variation proposed by the employer. For more information on the IMechE suite of contracts, see Practice note, IMechE/IET Model Forms of Contract.
3. Delay and concurrent delay
3.1 Following the decision of the Inner House in City Inn Ltd v Shepherd Construction Ltd [2010] ScotCS CSIH 68, where there is concurrent delay caused by both the contractor and employer, which of the following reflects English law (one point):
(a) The contractor does not get an extension of time.
(b) The contractor gets an extension of time.
(c) The court will apportion the delay between the parties.
(d) The court will apply the "but for" test to determine whether or not the contractor is entitled to an extension of time.
(e) The court will apply the prevention principle.
3.2 Where a contractor has submitted a programme indicating completion one week before the contractual completion date, and the contractor is then delayed by the employer by one week, and in fact completes on the contractual completion date:
(a) The contractor is entitled to one week's prolongation costs.
(b) The contractor is entitled to its prolongation costs during the week to the extent it can show they were caused by the employer.
(c) The contractor is not entitled to its prolongation costs during the week.
Statement (c) is correct. There is no right to complete prior to contractual completion date (Glenlion Construction v The Guinness Trust [1988] 39 BLR 89).
4.1 Which of the following statements is true about the Local Democracy, Economic Development and Construction Act 2009 (LDEDC Act 2009) (there may be more than one):
(a) Third parties may give section 110A payment notices.
(b) If the payer fails to give a timely section 110A payment notice the payee may give a payment notice at any time before the final date for payment.
(c) The payer is not obliged to give a "withholding notice" if the payee goes insolvent before the date upon which the payer is required to give such withholding notice.
(d) The adjudication provisions of a construction contract are required to be in writing.
In statement (b), the payee can give a payment notice at any time.
In statement (c), the payer is only let off giving a withholding notice, or pay less notice (in the new terminology), where the payee becomes insolvent after the date upon which the payer is required to give the notice.
The Department for Business, Innovation and Skills (BIS) originally indicated that the amended Construction Act 1996 may apply to construction contracts entered into on or after 1 April 2011, but October 2011 now seems more likely. However, no final date has been announced.
5. Bribery Act 2010
5.1 When does the Bribery Act 2010 come into force?
(a) It is already in force in its entirety.
(b) April 2011.
(c) October 2011.
(d) It is already in force in its entirety apart from section 7(2) (adequate procedures defence), which comes into force in April 2011.
5.2 In order to secure a conviction for bribing another person under the Bribery Act 2010, a prosecutor must prove an element of dishonesty or corrupt intent (one point). True or false?
6.1 Your client, Mr Beasley, wishes to terminate a building contract he has entered into with YHC. It is an unamended JCT Design and Build Contract, 2005 edition, Revision 2 2009. He asks you which of the following statements apply to section 8 (Termination) of his JCT contract:
(a) It contains provisions allowing Mr Beasley to terminate at any time for his convenience.
(b) It provides that Mr Beasley can terminate once appropriate default notices have been given and the contractor has been given time to remedy a default (other than insolvency and corruption where termination is immediate).
(c) It contains the parties' sole and exclusive rights in the event of termination under the contract.
(d) It is without prejudice to any other rights and remedies of Mr Beasley or the contractor (as appropriate).
6.2 Mr Beasley also asks you which of the following apply to his JCT contract:
(a) YHC is entitled to recover its lost profit on the contract if terminated due to Mr Beasley's default.
(b) The contract terminates automatically in the event of insolvency of YHC.
(c) Provisions of the contract which relate to payment or release of retention cease to apply upon the insolvency of YHC, whether the contract is terminated or not.
(d) Mr Beasley can sell all plant and equipment belonging to YHC to pay for completing the remainder of the works.
7.2 In an adjudication, the losing responding party has complied with the adjudicator's decision and paid sums to the winning party. It now wants to challenge the adjudicator's decision by legal proceedings and recover sums paid in compliance with it, but the underlying cause of action is statute barred. Which of the following statements is a correct summary of the legal position:
(a) The responding party cannot now recover these sums in legal proceedings: the claim is statute barred.
(b) The responding party can bring legal proceedings seeking a negative declaration only (that is, a declaration that it has no liability to the referring party).
(c) The responding party can bring legal proceedings to recover these sums and, if successful, to be repaid all sums paid. A term can be implied into the contract to this effect and this implied term creates a new cause of action at the time of payment in compliance with the adjudicator's decision.
Statement (c) is correct. This is a claim to which section 5 of the Limitation Act 1980 applies, because it is a claim founded on a simple contract, so that the losing party has 6 years from the date of payment in which to bring legal proceedings to recover that payment. This issue was recently considered by the TCC in Jim Ennis Construction Ltd v Premier Asphalt Ltd [2009] EWHC 1906 (TCC) (see Legal update, Accrual of cause of action and limitation periods in adjudication).
8. Contribution
8.1 Which of these statements is false?
(a) Generally, a claimant bringing a claim for breach of contract against parties who are jointly liable under the same contract must join both parties into the proceedings to enforce the promise.
(b) Generally, a claimant bringing a claim against parties who are jointly liable in tort must join both parties into the same proceedings.
(c) Parties who are jointly liable to a claimant in tort are also always severally liable.