What's on Practical Law?

Costs penalty for unreasonable conduct when drawing up court order (High Court)

Practical Law UK Legal Update Case Report 5-525-2797 (Approx. 4 pages)

Costs penalty for unreasonable conduct when drawing up court order (High Court)

by PLC Dispute Resolution
In Webb Resolutions Ltd v JV Ltd [2013] EWHC 509 (TCC), the court considered the conduct of the party's counsel and solicitors in preparing and agreeing a draft order made by a judge at a case management conference. The court ordered the claimant to pay the costs unnecessarily incurred as a result of its conduct. (free access)

Speedread

The court has ordered a claimant to pay the defendant's costs incurred as a result of the claimant's conduct in agreeing and drawing up the terms of a court order made at a case management conference (CMC).
Edwards-Stuart J found that the draft order prepared by the claimant bore no resemblance to the directions he had made at the CMC. When the defendant prepared an appropriate draft order, the claimant suggested extensive amendments to it. The claimant finally agreed the form of order, more than three months after the CMC, to avoid the costs of attending the restored hearing. The judge said that the claimant's conduct had been unreasonable and wholly unacceptable.
The facts of the case are very unusual, but the decision is a reminder that solicitors and counsel have a duty to give effect to court orders. They must not to attempt to manipulate them to their own perceived advantage. (Webb Resolutions Ltd v JV Ltd (t/a Shepherd Chartered Surveyors) [2013] EWHC 509 (TCC).)

Background

The procedure on drawing up court orders is set out in CPR 40 and Practice Direction (PD) 40B (see Practice note, Interim hearings: an overview: Drawing up the order).
The usual practice in the Technology and Construction Court (TCC) is for the court to ask the claimant or applicant's lawyers to prepare a draft order for agreement by the defendant or respondent's lawyers (paragraph 5.8.1, TCC Guide).
Parties to litigation are required to help the court to further the overriding objective (CPR 1.3). The TCC Guide expressly provides that a judge may impose costs sanctions if he concludes that one party is not reasonably co-operating with the other parties (paragraph 5.1.2, TCC Guide).

Facts

This decision relates to a professional negligence claim against a surveyor in the TCC.
At a case management conference (CMC) on 23 November 2012, Edwards-Stuart J ordered that certain issues (referred to as the assignment and lending issues) should be dealt with first. The issues relating to the actual valuations, if they arose, would be heard separately. The judge gave directions, in particular, limiting disclosure and exchange of evidence to the assignment and lending issues. He ordered that the costs of the CMC be reserved to the first trial.
The judge asked the claimant's counsel and solicitors to prepare a draft order. The subsequent conduct of the parties is relevant to the decision and, therefore, it is necessary to provide some detail. The following events took place:
  • The claimant's counsel sent to the defendant's counsel a draft order on 26 November.
  • The defendant's counsel and solicitors (RPC) did not agree that the draft order properly reflected what the judge had ordered, and provided their own draft order on 10 December.
  • The claimant's solicitors (RK) returned the defendant's draft with extensive amendments on 21 December.
  • RPC responded on 11 January 2013, saying that they could not agree the claimant's amendments.
  • RK wrote to the court on 16 January, stating they they were "experiencing great difficulty in drafting the order in a way which will give effect to the court's wishes but will avoid duplication of time and costs".
  • RPC then provided their draft order to the court.
  • The judge's clerk informed the parties that the order should be in the form prepared by RPC, and reminded the claimant that it could apply to vary the order.
  • The CMC was restored for hearing on 8 March.
  • On 5 March, RK consented to the defendant's form of order, to avoid the costs of attending the restored CMC.
Edwards-Stuart J directed that the restored CMC hearing should go ahead. RPC asked the claimant to pay their costs incurred as a result of the claimant not agreeing to the order made by the court. The claimant objected. Among its grounds for objections was that this was contrary to the order reserving costs to the trial judge.

Decision

Edwards-Stuart J ordered that his previous costs order be varied so that the costs incurred in agreeing or drawing up the terms of the 23 November 2012 order would be excluded from the costs to be reserved to the trial judge. He then ordered the claimant to pay £6,925 in respect of the defendant's costs.
Edwards-Stuart J said that, when he made the costs order at the CMC, it had not crossed his mind that one party would seek to introduce fundamental changes to the order, and that it would take three and a half months to agree it.
If a party is required to draw up an order, the party's solicitors and counsel have a duty to produce a draft that fairly reflects what they think the judge decided or directed. Edwards-Stuart J said that the claimant's draft order had borne "almost no relation" to what he had directed at the CMC. RK had, the judge said, drafted an order that reflected the directions that they or their clients would have liked. This was wholly unacceptable: "it is not just unreasonable, it is verging on the contumelious" (paragraph 19, judgment). He also commented that RK's statement in its 16 January letter to the court was disingenuous.
The judge considered that RPC's draft order had reflected what he had ordered, and that RPC were wholly justified in resisting RK's amendments. In the circumstances, the defendant should not have to pay the costs that were quite unnecessarily incurred as a result of the claimant's conduct.

Comment

The facts of this case are highly unusual but, by making a costs order against the claimant, the judge has given a very clear warning to those involved in drafting interim orders.
"In my judgment, what occurred in this case must not happen again. Solicitors and counsel are to give effect to court orders; they are not to attempt to manipulate them to their own or their client's perceived advantage."
(Paragraph 21, judgment.)
Where the parties cannot agree precisely what the court has ordered, they should raise the matter with the judge, who will usually be able to resolve the matter without a hearing.
End of Document
Resource ID 5-525-2797
© 2024 Thomson Reuters. All rights reserved.
Published on 19-Mar-2013
Resource Type Legal update: case report
Jurisdictions
  • England
  • Wales
Related Content