Questions and answers for the Berwin Leighton Paisner construction law Christmas quiz 2011. (Free access.)
Questions and answers
This article sets out the questions and answers for the Berwin Leighton Paisner construction Christmas quiz 2011.
The answers are revealed by clicking on the note below each question.
Construction Act 1996
Question 1
Which of the following statements is true (there may be more than one)?
(a) The statutory right to refer a dispute to adjudication under the Construction Act 1996 (as amended) only arises where the construction contract is in writing.
(b) The statutory right to refer a dispute to adjudication under the Construction Act 1996 (as amended) applies to all construction contracts whether wholly in writing, partly in writing or wholly oral.
(c) The statutory right to refer a dispute to adjudication under the Construction Act 1996 (as amended) applies to all construction contracts whether wholly in writing, partly in writing or wholly oral provided that the adjudication provisions are in writing.
(d) The statutory right to refer a dispute to adjudication under the Construction Act 1996 (as amended) applies to all construction contracts whether wholly in writing, partly in writing or wholly oral, however, where the contract is wholly oral, the adjudication provisions of the Scheme for Construction Contracts 1998 will apply.
(b) The statutory right to refer a dispute to adjudication under the Construction Act 1996 (as amended) applies to all construction contracts whether wholly in writing, partly in writing or wholly oral.
(d) The statutory right to refer a dispute to adjudication under the Construction Act 1996 (as amended) applies to all construction contracts whether wholly in writing, partly in writing or wholly oral, however, where the contract is wholly oral, the adjudication provisions of the Scheme will apply.
For information on the changes to Part II of the Housing Grants, Construction and Regeneration Act 1996 (Construction Act 1996), introduced by Part 8 of the Local Democracy, Economic Development and Construction Act 2009 (LDEDC Act 2009), see Construction Act 1996 changes toolkit.
Question 2
Which of the following statements is true (there may be more than one)?
(a) Third parties may give section 110A payment notices.
(b) The due date for payment can be fixed by reference to the payer's payment notice.
(c) The payer is not obliged to give a "pay less notice" if the payee goes insolvent before the date upon which the payer is required to give such pay less notice.
Your construction contract contains a tiered dispute resolution clause providing that when a dispute arises it must first be referred to the CEO of each party to try and reach an amicable resolution. Failing this the dispute may be referred to adjudication (the adjudication provision contains all of the mandatory requirements of the Construction Act 1996 (as amended)). A dispute has arisen - what is your advice to the client?
(a) The dispute must be referred to the CEOs first as this is what the contract says.
(b) The dispute can be referred to adjudication immediately and the contractual adjudication procedure will apply as it is Act-compliant.
(c) The dispute can be referred to adjudication immediately and the Scheme for Construction Contracts 1998 will apply.
The cost to an employer of mitigating the effects of a delay caused by a contractor breaching its obligations under the contract (for example, by negligently causing a fire) would not, in principle, fall within the scope of the liquidated damages clause. The employer retains a right to recover such losses under the first limb of Hadley v Baxendale. True or false?
Liquidated damages (LDs) are an exclusive remedy for delay and unliquidated damages cannot be recovered for other breaches of obligation which lead to a delay. The costs of mitigating any delay incurred by an employer cannot be recovered in addition to LDs.
In Biffa Waste Services v MEH & Others [2008] EWHC 6, it was agreed that Biffa (the contractor) would pay LDs in the event of delayed completion. The clause stated that the LDs would be "the only monies due from the contractor for such default", but also that the payment of LDs would be "without prejudice to any other right or remedy" of MEH (the employer). Delay resulted from a fire, caused by one of Biffa's sub-contractors. MEH argued that the LDs clause only related to damages for the breach of Biffa's obligation to complete on time and that it could also recover unliquidated damages for other breaches of obligation which led to the delay. The court held that the LDs were the only remedy for delay. MEH could not recover costs of mitigation in addition to LDs. The judge said that it is not possible to draw a distinction between a "simple" failure to complete and the failure to complete caused by breach of another obligation. If there is a failure to complete, LDs are the only remedy, whether the failure is a pure failure to complete or arises out of another breach.
Which of the following statements about design liability is true?
(a) The common law imposes on a professional person and a design and build contractor the same standard, that is, a standard of reasonable skill and care.
(b) The Supply of Goods and Services Act 1982 (as amended by the Sale and Supply of Goods Act 1994) provides that in a contract for the supply of a service where the supplier is acting in the course of a business, there is an implied term that the supplier will carry out the service with reasonable care and skill.
(c) Professional persons cannot delegate their design duty to third parties in any circumstances.
(d) A provision in a professional appointment which seeks to impose an absolute obligation on a professional person is unenforceable.
(b) The Supply of Goods and Services Act 1982 (as amended by the Sale and Supply of Goods Act 1994) provides that in a contract for the supply of a service where the supplier is acting in the course of a business, there is an implied term that the supplier will carry out the service with reasonable care and skill.
Which of the following statements is true about an unamended JCT Design and Build Contract, 2011 edition (there may be more than one)?
(a) The Contractor's design liability is absolute: he warrants that the Works, when complete, will achieve specific results set out in the contract.
(b) The Contractor's design liability is one of reasonable skill and care only.
(c) The Contractor has no responsibility for any design contained in the Employer's Requirements.
(d) The Contractor is responsible for any mistake or inaccuracy in the design of the Works and for any discrepancy or divergence between the Employer's Requirements and the Contractor's Proposals.
Which of the following statements is true (there may be more than one)? "Practical completion" should be certified:
(a) When the work to be done under the contract is complete in all respects and all patent and latent defects have been remedied.
(b) When the work to be done under the contract is complete in all respects, including any de minimis items, and all patent defects have been remedied.
(c) When the work to be done under the contract is complete in all respects apart from de minimis work and all patent defects have been remedied.
(d) In an unamended JCT 2011, when the Works are complete, the conditions precedent have been satisfied and there are no apparent defects.
(c) When the work to be done under the contract is complete in all respects apart from de minimis work and all patent defects have been remedied.
(d) In an unamended JCT 2011 edition contract, when the Works are complete, the conditions precedent have been satisfied and there are no apparent defects.
Which of the following statements is true (there may be more than one)? Under a JCT 2011 edition contract:
(a) If the Employer makes early use of the works practical completion is deemed to have occurred.
(b) If the Employer uses all of the Works for the purpose for which they were intended prior to the issue of the Practical Completion Certificate, practical completion is deemed to have occurred.
(c) If the Employer takes possession of part of the Works prior to the issue of the Practical Completion Certificate, practical completion is deemed to have occurred for that relevant part.
(d) If the Employer takes possession of the whole of the works prior to the issue of the Practical Completion Certificate, practical completion is deemed to have occurred for the whole of the Works.
(e) Exclusive possession is not a determining factor in deciding whether practical completion is deemed to have occurred.
(c) If the Employer takes possession of part of the Works prior to the issue of the Practical Completion Certificate, practical completion is deemed to have occurred for that relevant part.
(d) If the Employer takes possession of the whole of the works prior to the issue of the Practical Completion Certificate, practical completion is deemed to have occurred for the whole of the Works.
True or false? A party which terminates a contract for breach under a contractual provision thereby waives any right that he might have to accept a repudiatory breach.
True or false? A party which serves a contractual notice to terminate too early because it has mistakenly calculated the notice period is treated as having repudiated the contract.